PMP Exam Questions
60 Practice Questions With Answers and Explanations (2026)
60 free, original PMP practice questions for the 2026 exam, with answers and clear explanations, grouped by domain, plus the question types you will meet and a simple plan to practise well.
60 free PMP exam questions for 2026 with answers and explanations, grouped by People, Process and Business Environment, plus tips to practise and review.
By Brolly Academy Team · Brolly Academy · Updated 22 October 2026

Table of Contents
1. What PMP exam questions look like in 2026
3. How to answer PMP scenario questions
4. People domain practice questions (Q1 to Q20)
5. Process domain practice questions (Q21 to Q44)
6. Business Environment domain practice questions (Q45 to Q60)
7. How to score and review your practice
8. How to practise for the PMP exam
Quick answer
PMP exam questions are mostly scenario-based questions that ask what a project manager should do next, and the 2026 exam has 180 of them in 240 minutes across three domains: People, Process and Business Environment. PMI (Project Management Institute) updated the PMP (Project Management Professional) exam in July 2026. The new outline adds case-study and graphic-based questions and puts more weight on business value, AI, sustainability and stakeholder engagement. This article gives you 60 original practice questions with answers and explanations so you can test yourself today.
- Exam size: 180 questions (170 scored, 10 unscored), 240 minutes, two 10-minute breaks
- Domains: People 33%, Process 41%, Business Environment 26%
- Approaches: about 40% predictive, about 60% agile and hybrid
- New question types in 2026: case or scenario, and graphic-based
- This page: 60 practice questions (20 People, 24 Process, 16 Business Environment)
Key takeaways
- The PMP exam tests judgement, not memory. Most questions describe a situation and ask for the best next step.
- The Business Environment domain grew from 8% to 26% in the July 2026 outline, so expect many questions on governance, compliance, value and change.
- Agile and hybrid together make up about 60% of the exam, so you must be comfortable with both servant leadership and plan-driven control.
- Read the last line of each question first, remove the clearly wrong options, then choose the answer that a calm, proactive, collaborative project manager would pick.
- Practice questions are for learning. Review every wrong answer and write down why the right option is better.
1. What PMP exam questions look like in 2026
Short answer: You get 180 questions in 240 minutes. 170 are scored and 10 are unscored pretest questions. The outline does not say which ones are unscored, so treat every question as if it counts. Questions come from three domains and mix predictive, agile and hybrid situations.
All exam facts in this section come from the official PMP Examination Content Outline, July 2026 (PMI, July 2026, checked October 2026).
A few points matter for how you practise:
- Breaks lock sections. The first break comes after the case-study section. The second comes about midway through the independent questions. Once you start a break, you cannot go back to the section before it.
- Weights shifted. PMI's new-exam page (checked October 2026) says People moved from 42% to 33%, Process from 50% to 41%, and Business Environment from 8% to 26%. Older question banks may under-represent business topics.
- New themes. The same PMI page says the new exam adds AI, sustainability and stakeholder engagement in project-based scenarios and focuses more on outcomes, value and business impact.
With a 240-minute limit for 180 questions, you have about 80 seconds per question on average. Long case studies take more time, so build speed on the short ones.
For the full exam format, scheduling rules and exam-day tips, read our guide to the PMP exam.
2. PMP exam question types
Short answer: Most questions are multiple choice with one correct answer. You will also see multiple-response questions, new case or scenario questions, new graphic-based questions and, at test centres, drag-and-drop style formats such as matching and hotspot.
The July 2026 outline lists these question types (PMI, July 2026):
What this means for you:
- If you test online, expect single-response, multiple-response, case and graphic-based questions.
- If you test at a centre, also practise matching, hotspot and pull-down formats so the screen does not surprise you.
- Graphic questions usually show a burndown chart, a Kanban board, a schedule or a risk chart. Practise reading these quickly.
In this article, every question is written as text. Where a question is "graphic-based", we describe the chart in words. Multiple-response questions say "Choose two".
3. How to answer PMP scenario questions
Short answer: Find what the question really asks, identify whether the setting is predictive, agile or hybrid, rule out options that avoid the problem or skip steps, and pick the action a proactive, collaborative project manager would take first.
Use this five-step method on every question:
- Read the last line first. Is it asking what to do first, what to do next, or what should have been done earlier? The answer changes with that word.
- Spot the approach. Words like sprint, backlog, product owner and team-led mean agile. Baseline, change control board and work package mean predictive. A mix means hybrid.
- Remove the escape options. Answers that escalate at once, ignore the problem, blame someone or make a decision alone are rarely best.
- Prefer understanding before action. If the cause is unclear, the best first step is often to talk to the person, analyse the impact or check the plan.
- Follow the process. In predictive work, changes go through change control. In agile work, new needs go to the product backlog and the product owner prioritises them.
Think of the PMP answer as what an ideal project manager would do in a well-run organisation, not what busy managers sometimes do in real life. Calm, honest, collaborative and value-focused choices win.
4. People domain practice questions (Q1 to Q20)
Short answer: People questions test how you lead and support the team and stakeholders: building a shared vision, managing conflict, coaching, negotiating and engaging stakeholders. This domain is 33% of the exam (PMI, July 2026).
Q1. Two developers in conflict
Two senior developers on your agile team argue strongly about which architecture to use. The argument is slowing down sprint planning. What should you do first?
- A. Escalate the matter to their functional manager
- B. Choose the architecture yourself to save time
- C. Meet both developers to understand their concerns and help them reach a solution together
- D. Ask the whole team to vote immediately
Answer: C
Explanation: Collaborating to solve the problem gives the best long-term result because it addresses the root cause and keeps trust. Escalating or deciding alone removes ownership from the team. A quick vote may leave one expert unconvinced.
Q2. A new team from three countries
You are forming a hybrid team with members in India, Poland and the US. In the first week there are misunderstandings about response times and meeting etiquette. What is the best action?
- A. Send everyone the company's HR policy
- B. Facilitate a session where the team creates a team charter with working agreements
- C. Set strict rules yourself and share them by email
- D. Wait for the team to settle down naturally
Answer: B
Explanation: A team charter created by the team sets shared ground rules and builds ownership. Rules imposed by the project manager are less likely to be followed. Waiting lets small problems grow.
Q3. A team member misses stand-ups
A tester has missed four daily stand-ups this sprint, and the quality of their work has dropped. What should you do first?
- A. Report the tester to HR
- B. Raise the issue in front of the team at the next stand-up
- C. Talk privately with the tester to understand what is happening
- D. Replace the tester with another resource
Answer: C
Explanation: Before acting, you need to understand the cause. A private conversation is respectful and may reveal a personal or workload issue you can help solve. Public criticism or quick replacement damages trust.
Q4. A resistant finance head
The finance head believes your project will reduce their department's budget and has started to block approvals. What is the best way to handle this?
- A. Ask the sponsor to order the finance head to cooperate
- B. Meet the finance head to understand their concerns and update the stakeholder engagement plan
- C. Leave the finance head out of future communications
- D. Proceed without their approvals
Answer: B
Explanation: Resistant stakeholders need active engagement. Understanding their concerns helps you find common ground and plan how to move them toward support. Excluding them or going around them usually increases resistance.
Q5. The team asks you to assign tasks
Your newly formed agile team keeps asking you to assign their daily tasks. What should you do?
- A. Assign the tasks so work is not delayed
- B. Coach the team to pull work from the sprint backlog and decide among themselves
- C. Ask the product owner to assign the tasks
- D. Ask the functional managers to assign the tasks
Answer: B
Explanation: In agile teams, the project manager acts as a servant leader who builds self-organisation. Coaching the team to pull work develops ownership. Assigning tasks yourself keeps the team dependent on you.
Q6. No shared view of success
At the kick-off, the sponsor says success means "faster customer onboarding", while the team thinks success means "launching the new app on time". What is the best next step?
- A. Follow the sponsor's view because the sponsor funds the project
- B. Follow the team's view because they do the work
- C. Run a workshop to agree on a common vision and measurable success criteria
- D. Record both views and move on
Answer: C
Explanation: Developing a common vision is one of the first People tasks in PMI's outline. A shared vision with measurable outcomes keeps everyone pulling in the same direction. Ignoring the gap leads to conflict later.
Q7. A key engineer is leaving
A senior engineer who holds key knowledge about a legacy system will leave the company in two weeks. What should you do?
- A. Ask HR to delay the exit
- B. Plan knowledge transfer now through pairing, recorded walkthroughs and documentation
- C. Hire a replacement after the engineer leaves
- D. Remove the legacy work from the scope
Answer: B
Explanation: Proactive knowledge transfer reduces the risk of losing critical knowledge. Pairing and documentation spread knowledge across the team. Waiting until after the exit creates a gap.
Q8. Blind trust in an AI tool
Your team uses an AI assistant to draft test cases. A junior tester copies AI output without checking, and several test cases miss key business rules. What is the best action?
- A. Ban the AI tool for the whole team
- B. Agree team guidelines for reviewing AI output and coach the junior tester on checking it
- C. Ask the junior tester to stop testing
- D. Ignore it because the tool usually works
Answer: B
Explanation: AI tools can speed up work, but people stay accountable for the result. Clear review guidelines and coaching fix the root cause while keeping the benefit of the tool. A blanket ban is an overreaction.
Q9. Little time-zone overlap
Your distributed team has only two overlapping working hours each day. Decisions are slow. What should you do?
- A. Ask everyone to work the same hours as the head office
- B. Work with the team to agree core collaboration hours and use shared tools for asynchronous updates
- C. Hold all meetings at the time that suits you
- D. Split the team into separate projects
Answer: B
Explanation: Agreeing core hours and good asynchronous practices respects everyone while keeping decisions moving. Forcing one time zone on everyone hurts morale. Splitting the team is not justified by this problem.
Q10. Low morale after a failed release
A release failed in production, and the team feels demotivated. Some members are blaming each other. What should you do?
- A. Find the person responsible and document it
- B. Hold a blameless retrospective focused on learning and improvement actions
- C. Skip the retrospective to save time for fixes
- D. Ask the sponsor to speak to the team
Answer: B
Explanation: A blameless retrospective helps the team learn, rebuild trust and agree improvements. Blame makes people hide problems in future. Skipping reflection risks repeating the failure.
Q11. Two managers want the same person
Two functional managers both want the same database specialist for the same weeks. Your project needs the specialist too. What is the best action?
- A. Escalate to the sponsor immediately
- B. Meet both managers to negotiate a plan based on project priorities and timelines
- C. Ask the specialist to choose
- D. Book the specialist first before the others do
Answer: B
Explanation: Negotiation with the resource owners is the right first step. You can often find a schedule that works for all. Escalate only if negotiation fails.
Q12. An angry stakeholder in a meeting
A key client stakeholder becomes angry in a review meeting and criticises the team loudly. What should you do?
- A. Defend the team strongly in the meeting
- B. End the meeting at once
- C. Stay calm, acknowledge the concern, and arrange a one-to-one follow-up to understand the issues
- D. Ask the stakeholder to send concerns by email only
Answer: C
Explanation: Emotional intelligence means staying calm and showing you have heard the person. A private follow-up allows an honest discussion of the real concerns. Arguing in public makes things worse.
Q13. Building a high-performing team (Choose two)
Which two actions best help build a high-performing team?
- A. Recognise and reward team achievements
- B. Review every task each person does every day
- C. Provide training to close skill gaps
- D. Share information only on a need-to-know basis
- E. Publicly name team members who make mistakes
Answer: A and C
Explanation: Recognition and skill development raise motivation and capability. Micro-management, secrecy and public blame reduce trust and performance.
Q14. A new tool, a skills gap
Your organisation is moving the team to a new cloud testing tool next month. Most team members have never used it. What should you do first?
- A. Delay the tool until the project ends
- B. Assess the team's skill gaps and plan training before the switch
- C. Let team members learn on the job
- D. Hire external testers who know the tool
Answer: B
Explanation: Assessing gaps and planning training is the proactive choice. It reduces the risk of delays when the tool goes live. Hiring outsiders may be an option later, but it is not the first step.
Q15. Breaking the working agreement
The team agreed not to interrupt each other in meetings. One member keeps interrupting, and others look frustrated. What is the best approach?
- A. Remove the member from meetings
- B. Remind the team of its working agreement and encourage the team to hold each other to it
- C. Ignore it because the member is a high performer
- D. Rewrite the working agreement yourself
Answer: B
Explanation: Working agreements belong to the team. Reminding everyone and supporting the team to enforce its own rules builds a healthy culture. Ignoring the behaviour weakens the agreement.
Q16. A new stakeholder appears mid-project
Halfway through the project, you learn that a regulatory affairs team must approve the product before launch. They were not in your stakeholder register. What should you do first?
- A. Wait until launch to involve them
- B. Add them to the stakeholder register, analyse their interest and influence, and plan how to engage them
- C. Ask the sponsor to get their approval
- D. Change the launch date
Answer: B
Explanation: Stakeholder identification continues throughout the project. Once you find a new stakeholder, you analyse them and plan engagement. Changing the date before you understand their needs is premature.
Q17. The product owner is rarely available
The product owner attends only one meeting per sprint, and the team often waits days for answers. What should you do?
- A. Make the decisions for the product owner
- B. Discuss the impact with the product owner and agree on regular availability or a delegate with authority
- C. Complain to the sponsor
- D. Let the team guess the requirements
Answer: B
Explanation: An unavailable product owner is an impediment. Showing the impact and agreeing a solution addresses the cause. Guessing requirements creates rework.
Q18. Wide spread in estimates
During planning poker, estimates for one user story range from 2 to 13 points. What should happen next?
- A. Take the average
- B. Use the estimate of the most senior developer
- C. Ask the people with the highest and lowest estimates to explain their thinking, then estimate again
- D. Skip the story this sprint
Answer: C
Explanation: A wide spread shows different understanding of the work. Discussing the extremes brings out hidden risks or simpler solutions. Averaging hides the disagreement.
Q19. A sponsor wants a promise
The sponsor asks you to promise a go-live date in a client meeting tomorrow. The team has not estimated the work yet. What should you do?
- A. Give the date the sponsor wants
- B. Refuse to give any date
- C. Work with the team to estimate quickly and give the sponsor a realistic forecast with options
- D. Add a large buffer to a guessed date
Answer: C
Explanation: Honest, team-based estimates protect trust and credibility. Giving options helps the sponsor make an informed promise. Guessing, even with a buffer, is not transparent.
Q20. A quiet team member
A team member from a different cultural background rarely speaks in group meetings, though their written ideas are strong. What is the best action?
- A. Ask them to speak more in every meeting
- B. Accept that they will not contribute verbally
- C. Create safe ways to contribute, such as one-to-one check-ins, written input and round-robin discussion
- D. Give their work to someone more vocal
Answer: C
Explanation: Inclusive leadership adapts to different styles. Several channels for input help every member contribute fully. Pressure or exclusion wastes good ideas.
5. Process domain practice questions (Q21 to Q44)
Short answer: Process questions test how you plan and deliver: integrated planning, scope, schedule, cost, quality, risk, procurement, communication and value-based delivery. This is the largest domain at 41% of the exam (PMI, July 2026).
Q21. The charter is approved
The sponsor has just approved the charter for a predictive office construction project. What should you do next?
- A. Start construction work
- B. Develop the integrated project management plan with key stakeholders
- C. Sign contracts with all suppliers
- D. Close the initiating phase report
Answer: B
Explanation: After the charter, you plan before you execute. The integrated plan brings scope, schedule, cost, quality, risk and other plans together. PMI's outline starts the Process domain with this task.
Q22. A client asks for an extra feature
In a predictive project, the client asks for a new report that is not in the approved scope. What should you do first?
- A. Add the report because the client is important
- B. Refuse the request
- C. Analyse the impact on scope, schedule, cost and risk, then submit a change request
- D. Ask the team to build it in their free time
Answer: C
Explanation: Predictive projects use change control. You analyse the impact first, then the change control board or authorised person decides. Adding work without approval is scope creep.
Q23. A new request mid-sprint
During a sprint, a customer asks the team to add a new feature right away. What should happen?
- A. The team adds it to the current sprint
- B. The product owner adds it to the product backlog and prioritises it for a future sprint
- C. The project manager rejects it
- D. The team cancels the sprint
Answer: B
Explanation: The sprint goal should stay stable. New needs go to the product backlog, and the product owner orders them by value. The team can pick it up in a later sprint.
Q24. Earned value check
Your project shows these figures: planned value ₹45 lakh, earned value ₹40 lakh, actual cost ₹50 lakh. What is the status?
- A. Under budget and ahead of schedule
- B. Over budget and behind schedule
- C. Over budget and ahead of schedule
- D. Under budget and behind schedule
Answer: B
Explanation: CPI = EV / AC = 40 / 50 = 0.8, so you spend more than you earn (over budget). SPI = EV / PV = 40 / 45, about 0.89, so you are behind schedule. Any index below 1 is unfavourable.
Q25. An unexpected supplier strike
A supplier's workers go on strike. This was not in your risk register, and deliveries stop. What should you do?
- A. Wait for the strike to end
- B. Assess the impact, apply a workaround such as an alternate supplier, and update the issue log and risk register
- C. Tell the sponsor the project will be late
- D. Cancel the contract immediately
Answer: B
Explanation: An unplanned risk that has occurred is an issue and needs a workaround. You then record it and update risk analysis so similar risks are covered. Cancelling the contract without checking its terms may cause legal problems.
Q26. An opportunity for a discount
A supplier offers a 15% discount if you order equipment within the next 10 days. You want to make sure the project gets this benefit. Which risk response is this?
- A. Exploit
- B. Accept
- C. Transfer
- D. Mitigate
Answer: A
Explanation: Exploit is a response to a positive risk (opportunity) that makes sure it happens. Mitigate and transfer are responses to threats. Accept means taking no special action.
Q27. Repeated defects in UAT
Users find the same type of defect in every user acceptance test cycle. What is the best action?
- A. Add more testers at the end
- B. Do a root cause analysis and improve the process so defects are prevented
- C. Ask users to test less strictly
- D. Accept the defects as normal
Answer: B
Explanation: Quality management prefers prevention over inspection. Root cause analysis fixes the source, so the same defects stop appearing. More testing at the end only finds defects later.
Q28. Gold plating
A developer adds an extra dashboard the customer never asked for, thinking it will impress them. What should you do?
- A. Show it to the customer as a bonus
- B. Explain that unrequested work is not in scope and must go through the change process if needed
- C. Thank the developer and add it to the release
- D. Remove the developer from the team
Answer: B
Explanation: Gold plating adds cost, risk and testing effort without approval. Any new feature should go through the proper change or backlog process. Coaching the developer prevents a repeat.
Q29. An increment is rejected
The product owner rejects a sprint increment because user documentation is missing. The team thought documentation was not needed. What is the best action?
- A. Ask the product owner to accept it anyway
- B. Review and clarify the definition of done with the team and product owner
- C. Write the documentation yourself
- D. Remove documentation from all future work
Answer: B
Explanation: The problem is an unclear definition of done. Agreeing it together prevents the same rejection in future sprints. Working around it does not fix the cause.
Q30. Hybrid hardware and software
Your project builds a medical device. The hardware follows a predictive plan, and the software team works in two-week sprints. How should you plan delivery?
- A. Make the software team follow the hardware plan
- B. Make the hardware team run sprints
- C. Create an integrated release roadmap that aligns software increments with hardware milestones
- D. Manage the two teams as separate projects
Answer: C
Explanation: A hybrid approach uses each method where it fits and links them with an integrated plan. Aligning sprints to hardware milestones helps integration and testing. Forcing one method on both removes the benefit of hybrid.
Q31. Critical path delay, no extra budget
A critical path task is two weeks late. The sponsor will not approve extra budget. Which technique is most suitable to recover the schedule?
- A. Crashing
- B. Fast tracking
- C. Cutting testing without approval
- D. Reducing scope without telling the customer
Answer: B
Explanation: Fast tracking runs activities in parallel and does not usually add direct cost, though it adds risk. Crashing adds resources and cost. Cutting testing or scope without approval breaks quality and change rules.
Q32. A vendor misses quality terms
A vendor's deliveries repeatedly fail the quality standard written in the contract. What should you do first?
- A. Stop paying the vendor
- B. Review the contract terms and formally raise the issue with the vendor as the contract requires
- C. Find a new vendor immediately
- D. Accept the deliveries to avoid delay
Answer: B
Explanation: The contract is the legal basis of the relationship. Following its terms protects the project and gives the vendor a chance to correct. Stopping payment or switching vendors without due process can create legal risk.
Q33. Choosing a contract type
You need two extra analysts for three months, and the exact scope of their work is not yet clear. Which contract type fits best?
- A. Firm fixed price
- B. Time and materials
- C. Fixed price with incentive fee
- D. Cost plus award fee for a large build
Answer: B
Explanation: Time and materials contracts suit short staff augmentation where scope is not fully defined. Fixed price needs a clear scope. Cost-plus types are more common for larger, uncertain builds.
Q34. Too many emails
Stakeholders say they receive too many project emails and miss important updates. What should you do?
- A. Send even more emails marked urgent
- B. Review the communications plan with stakeholders and tailor the format and frequency, such as a weekly dashboard
- C. Stop sending updates
- D. Send updates only to the sponsor
Answer: B
Explanation: Communication should match what stakeholders need. Reviewing and tailoring the plan makes updates useful and visible. Stopping or cutting updates creates new risks.
Q35. After phase one
Phase one of your project just finished with several problems. Phase two starts next week. What should you do now?
- A. Wait until the project ends to collect lessons learned
- B. Capture lessons learned now and use them to adjust plans for phase two
- C. Start phase two as planned
- D. Ask the team to forget phase one
Answer: B
Explanation: Lessons learned should be captured throughout the project, not only at the end. Using them right away helps you avoid repeating mistakes in the next phase.
Q36. High velocity, low value
Your agile team's velocity has risen for four sprints, but the customer says the product still does not solve their problem. What should you do?
- A. Celebrate the higher velocity
- B. Work with the product owner and customer to review outcomes and reorder the backlog by value
- C. Ask the team to work faster
- D. Add more features
Answer: B
Explanation: Velocity measures output, not value. PMI's outline includes helping ensure value-based delivery. Checking outcomes with the customer and re-prioritising focuses the team on what matters.
Q37. A known risk occurs
A risk listed in your risk register occurs, and its planned response costs ₹3 lakh. Which reserve should pay for it?
- A. Management reserve
- B. Contingency reserve
- C. The team's training budget
- D. The sponsor's personal budget
Answer: B
Explanation: Contingency reserve covers identified risks (known unknowns) and is part of the cost baseline. Management reserve covers unidentified risks (unknown unknowns) and needs management approval.
Q38. A flat burndown chart (graphic-based)
A sprint burndown chart shows a steady downward line for the first four days, then a flat line for the next three days. What does this most likely mean, and what should happen?
- A. The team finished early; close the sprint
- B. Work has stalled, possibly due to blockers; raise it at the daily stand-up to find and remove impediments
- C. The chart is wrong; stop using it
- D. Add more work to the sprint
Answer: B
Explanation: A flat burndown means remaining work is not going down. The team should find out why at the stand-up and remove blockers. Ignoring the signal risks missing the sprint goal.
Q39. The customer says "looks good"
The customer tells you in a call that the final deliverable "looks good". What should you do next?
- A. Close the project immediately
- B. Obtain formal acceptance as defined in the project plan or contract
- C. Release the team and move on
- D. Send the final invoice only
Answer: B
Explanation: Verbal approval is not formal acceptance. Formal sign-off protects both sides and is needed before closing. After acceptance, you release resources, archive records and record lessons learned.
Q40. A work package is too big to estimate
The team cannot estimate a large work package in the WBS because it is too vague. What should you do?
- A. Use a random estimate
- B. Decompose the work package into smaller pieces, or plan it in more detail later using rolling wave planning
- C. Remove it from scope
- D. Ask the sponsor for the estimate
Answer: B
Explanation: Decomposition makes work small enough to estimate. If details are not yet known, rolling wave planning lets you plan near-term work in detail and future work at a higher level.
Q41. Tracking agile progress (Choose two)
Which two tools are most commonly used to show progress in an agile team?
- A. Burndown chart
- B. Stakeholder register
- C. Task board or Kanban board
- D. Procurement statement of work
- E. Risk breakdown structure
Answer: A and C
Explanation: Burndown charts and task boards make progress visible to everyone. The other options are planning or analysis documents, not progress trackers.
Q42. Work piling up in testing
On your Kanban board, many items are waiting in the "Testing" column while developers keep starting new items. What is the best action?
- A. Hire more developers
- B. Set work-in-progress limits and ask the team to help clear the testing queue
- C. Skip testing for low-risk items
- D. Add a new column called "Waiting"
Answer: B
Explanation: WIP limits stop the team from starting more than it can finish. Helping clear the bottleneck improves flow. Skipping testing harms quality.
Q43. One engineer is overloaded
A resource histogram shows one engineer is assigned 70 hours of work in week six. Some of that work has float. What should you do first?
- A. Ask the engineer to work overtime
- B. Use resource smoothing to move activities within their float
- C. Delay the whole project
- D. Remove the engineer from the project
Answer: B
Explanation: Resource smoothing adjusts activities within float, so the end date does not move. Overtime harms well-being and quality. Resource levelling, which may change the end date, comes in only if smoothing is not enough.
Q44. Two versions of requirements
The development and testing teams find they have been working from different versions of the requirements document. What should you do?
- A. Ask the testers to use the developers' version
- B. Set up version control so everyone works from one approved, current version
- C. Let each team keep its own copy
- D. Rewrite the requirements from scratch
Answer: B
Explanation: Configuration and version control create a single source of truth. This prevents rework and defects caused by mismatched documents.
6. Business Environment domain practice questions (Q45 to Q60)
Short answer: Business Environment questions test how your project fits the organisation and the world around it: governance, compliance, benefits and value, organisational change, external changes, sustainability and ethical use of AI. This domain jumped to 26% in the July 2026 outline (PMI, July 2026).
Q45. Who approves budget changes?
During execution, nobody is sure who can approve budget changes above ₹10 lakh. Decisions keep getting delayed. What should you do?
- A. Approve the changes yourself
- B. Work with the sponsor to define governance, including decision rights and escalation thresholds
- C. Stop all budget changes
- D. Ask finance to decide every change
Answer: B
Explanation: Defining and establishing project governance is the first task in PMI's Business Environment domain. Clear decision rights speed up approvals and protect everyone.
Q46. A new data-protection rule
A new data-protection regulation comes into force midway through your customer app project. What should you do first?
- A. Continue as planned
- B. Work with legal and compliance experts to assess the impact, then update requirements and plans through change control
- C. Remove all customer data from the app
- D. Delay the launch for a year
Answer: B
Explanation: Compliance with regulations is mandatory. Assessing the impact with experts tells you exactly what must change. Then you update the plan in a controlled way.
Q47. A sustainability target
Your client wants the new warehouse to cut its carbon footprint compared with the old one. How should you handle this?
- A. Treat it as a nice-to-have and ignore it if costs rise
- B. Include measurable sustainability criteria in the requirements, design and procurement decisions
- C. Leave it to the construction contractor
- D. Report on it only at the end of the project
Answer: B
Explanation: PMI's outline lists sustainability among compliance examples. Making it measurable and building it into requirements and supplier selection ensures it shapes decisions from the start.
Q48. Planning to measure benefits
The sponsor wants proof that your CRM project will reduce customer complaints after go-live. What should you do during planning?
- A. Promise the benefit in the charter
- B. Define measurable benefits, a benefit owner and a timeline in a benefits management plan
- C. Measure complaints only during the project
- D. Leave benefits to the operations team
Answer: B
Explanation: Benefits often appear after the project closes. A benefits management plan names who measures what and when. This links the project to business value.
Q49. Users resist a new system
Branch staff are resisting a new loan system and continue to use old spreadsheets. What is the best approach?
- A. Disable the spreadsheets immediately
- B. Support organisational change through clear communication of the reasons, training and change champions in each branch
- C. Report the staff to their managers
- D. Wait for them to adapt
Answer: B
Explanation: People adopt change when they understand why and feel supported. Training and local champions reduce fear and resistance. Force alone often creates workarounds.
Q50. The market shifts
A competitor launches a similar product, and market research shows one of your planned features now has little value. What should you do?
- A. Build the feature anyway because it is in the plan
- B. Review the business case with the sponsor and product owner and reprioritise or remove the feature
- C. Speed up the team
- D. Hide the research from stakeholders
Answer: B
Explanation: Projects must respond to the external environment. Reviewing the business case keeps the project focused on value. Building low-value features wastes money.
Q51. The business case no longer holds
Mid-project, a merger means your project's business case is no longer valid. What should you do?
- A. Finish the project as planned
- B. Inform the sponsor and recommend reviewing whether to continue, change or close the project
- C. Close the project yourself
- D. Keep the news within the team
Answer: B
Explanation: The sponsor owns the business case and decides whether the project continues. Your role is to raise the issue quickly with clear analysis. Ending or continuing on your own is outside your authority.
Q52. Client data and a public AI tool
A team member wants to paste confidential client data into a free public AI chatbot to summarise it. What should you do?
- A. Allow it because it saves time
- B. Stop it, check the organisation's AI policy and the client contract, and use only approved tools with proper data handling
- C. Allow it if the data is deleted afterwards
- D. Ask the client after the fact
Answer: B
Explanation: Confidentiality and compliance come first. Approved tools and clear policies let teams use AI safely. Sharing client data without permission can breach contracts and laws.
Q53. An audit finding on access control
An internal security audit finds that some team members have access to production systems they do not need. What should you do?
- A. Ignore it until the project ends
- B. Treat it as a compliance issue, plan the fix quickly and report progress through governance
- C. Remove access for the whole team
- D. Ask the auditors to change the finding
Answer: B
Explanation: Security is one of the compliance areas in PMI's outline. A quick, planned fix that is reported properly protects the organisation. Removing all access would stop the work unnecessarily.
Q54. A near-miss on site
A site engineer reports a near-miss where a worker almost fell from scaffolding. What should you do first?
- A. Record it and continue work
- B. Stop the unsafe work, make the area safe, investigate the cause and follow the health and safety policy
- C. Blame the worker
- D. Wait to see if it happens again
Answer: B
Explanation: Health and safety come before schedule. Stopping unsafe work, investigating and fixing the cause prevents a real accident. Ignoring a near-miss is a serious failure of compliance.
Q55. PMO templates slow the agile team
The PMO requires a 20-page status report every week. Your agile team feels it wastes time. What should you do?
- A. Stop sending the reports
- B. Work with the PMO to tailor reporting so it meets the PMO's needs with lighter agile artifacts
- C. Ask the team to work overtime on reports
- D. Escalate a complaint about the PMO
Answer: B
Explanation: Governance has a purpose, so work with it, not around it. Tailoring keeps the intent (visibility and control) while reducing waste. Ignoring the PMO damages trust.
Q56. A gift from a bidder
During vendor selection, a bidding vendor sends you an expensive gift. What should you do?
- A. Accept it quietly
- B. Decline the gift, follow the organisation's policy and disclose it
- C. Accept it and give the vendor a higher score
- D. Share it with the team
Answer: B
Explanation: Accepting gifts during selection creates a conflict of interest. Declining and disclosing protects fairness and your integrity. Organisational policy should guide the exact steps.
Q57. A heavy method for a small project
Your company's full methodology requires 40 documents. Your project is small, low-risk and lasts six weeks. What should you do?
- A. Produce all 40 documents
- B. Tailor the approach to the project's size and risk, agree it with governance and record why
- C. Skip all documentation
- D. Refuse the project
Answer: B
Explanation: Tailoring means adapting the method to fit the project. Agreeing and recording the choices keeps it transparent. Doing everything or nothing are both poor choices.
Q58. Signs of real value (Choose two)
Which two signs best show your project is delivering business value?
- A. Business KPIs from the business case are improving
- B. The team is fully busy every day
- C. Customer adoption of the new product is growing
- D. All tasks finished on their planned dates
- E. The project produced many documents
Answer: A and C
Explanation: Value is about outcomes, such as KPIs and adoption. Being busy, being on time and producing documents are outputs that may or may not create value.
Q59. Import duties rise
The government raises import duties on equipment your project needs. Costs will go up by 12%. What should you do?
- A. Absorb the cost silently
- B. Analyse the impact on the budget and business case, inform the sponsor and follow change control
- C. Buy cheaper equipment without approval
- D. Stop the project
Answer: B
Explanation: External changes can affect the business case. Analysing the impact and raising it formally lets the right people decide. Hidden changes create bigger problems later.
Q60. Operations is not ready
Two weeks before handover, the operations team says it is not ready to support the new system. What should you have done earlier, and what should you do now?
- A. Hand over anyway as planned
- B. Plan readiness and knowledge transfer with operations as part of the project, and now agree a short transition plan with them
- C. Ask the project team to run operations forever
- D. Delay handover with no plan
Answer: B
Explanation: Transition and readiness should be planned from the start so benefits continue after the project. Now, a clear transition plan with operations reduces risk at handover.
7. How to score and review your practice
Short answer: Track your scores by domain, review every wrong answer, and write one line on why the correct option is better. The review matters more than the score.
Use this simple method after each practice set:
Two patterns are common for Indian candidates who manage projects in IT services:
- Escalating too early. In many offices, escalation is normal. On the exam, you usually try to solve the problem with the people involved first.
- Choosing the predictive answer in agile settings. If the question mentions a product owner or sprint, think servant leadership and backlog, not change control boards.
8. How to practise for the PMP exam
Short answer: Start with the official exam content outline, study by domain, do short practice sets daily, then take full-length 180-question mock exams under timed conditions before booking your date.
Here is a simple practice plan:
- Read the outline first. PMI's July 2026 Examination Content Outline lists every task in each domain. Every good question maps to one of these tasks.
- Study one domain at a time. Follow the domain weights. Spend the most time on Process (41%), then People (33%) and Business Environment (26%). Our PMP syllabus guide breaks these down task by task.
- Do 20 to 30 questions a day. Small daily sets with full review beat one big weekend session.
- Practise all question types. Include multiple-response, case and graphic questions, not just simple multiple choice.
- Take full mocks. Sit full 180-question, 240-minute mocks with two breaks, the same way the real exam runs. This builds stamina.
- Check your materials. Make sure your question bank matches the July 2026 outline, with enough Business Environment, AI and sustainability questions.
- Avoid "dumps". Lists that claim to be real or leaked PMP questions are not reliable and do not build the judgement the exam tests.
A note on exam rules that affect your plan: you get a one-year eligibility period after you pay (or after you pass an audit, if selected), and you can take the exam up to three times in that period. Fees apply again for the second and third attempts. If you fail three times, you must wait one year from your last exam before you reapply for PMP. These rules come from the PMI Certification Handbook (PMI, revised June 2026) and the July 2026 outline. Rescheduling or cancelling within 30 days of your appointment costs US$70 plus taxes, about ₹6,633 at the Wise mid-market rate of about ₹94.75 per US dollar (Wise, 22 October 2026; an approximate estimate). Within 48 hours of the exam, you lose all fees. So book your date only when your mock scores are steady.
If you want the eligibility rules in full before you start practising, see PMP certification eligibility.
After you pass, PMP is not a one-time test. You keep it by earning 60 PDUs in each three-year cycle, as PMI's Continuing Certification Requirements Handbook explains (PMI, checked October 2026).
9. Common mistakes when practising PMP questions
Short answer: The biggest mistakes are memorising answers, using outdated question banks, ignoring agile and business questions, and never practising under real time limits.
- Memorising answers. The real exam uses different scenarios. Learn the reasoning, not the letter.
- Using old material only. Domain weights changed in July 2026. Banks built for the older outline may give too few Business Environment questions.
- Skipping explanations. Reading why the other options are wrong teaches you as much as the right answer.
- Reading too fast. Words like "first", "next" and "best" change the answer.
- Practising only short questions. Case studies and graphics take longer. Include them.
- Never timing yourself. Without timed mocks, you may run out of time on exam day.
Once you pass, you will likely face interviews where people test the same judgement in a different way. Our PMP interview questions guide helps you prepare for that next step. If you are deciding between agile and traditional roles, our comparison of Scrum Master vs project manager explains how the two jobs differ.
10. How Brolly Academy helps
Short answer: Brolly Academy offers PMP exam preparation and project management skills training in Hyderabad, in classroom and online modes, with a dedicated exam preparation module and an experienced trainer.
The Brolly Academy PMP certification course in Hyderabad is described on its course page (checked October 2026) like this:
- Format: 35 contact hours of instructor-led training over 4 weeks
- Modes: classroom and online, with weekday and weekend batches; online batches have flexible timings
- Next batch: Monday, 2 November 2026
- Trainer: Mr. Raju, PMP trainer with 15+ years of experience
- Syllabus: 13 modules, including Predictive Project Management, Agile and Scrum, Hybrid Project Management, AI in Project Management (Gen AI), Leadership and Business Environment, Risk, Quality and Resource Management, and PMP Exam Preparation
- Fees: from ₹10,999 (Video Recording Plan); Online Course ₹30,000; Classroom Training ₹40,000; EMI available
The modules on hybrid delivery, AI and business environment line up well with the areas the July 2026 exam stresses.
One important point: according to PMI's PMP certification page (PMI, October 2026), from 1 December 2026 live classes count toward the 35-hour training requirement only when they come from a PMI Authorized Training Partner, a China Registered Education Provider or an eligible accredited academic programme. Self-paced courses from any organisation still count. Check PMI's current rules for your training hours before you apply. Treat Brolly's course as exam preparation and skills training.
Practise PMP questions with an experienced trainer
Want help turning practice scores into a pass? Join Brolly Academy's PMP exam preparation in Hyderabad, in classroom or online, with a dedicated exam preparation module and Mr. Raju, a PMP trainer with 15+ years of experience. The next batch starts on Monday, 2 November 2026. Call +91 81868 44555 to ask about batch timings.
Frequently asked questions
How many questions are on the PMP exam in 2026?
The PMP exam has 180 questions. According to PMI's July 2026 exam content outline, 170 of these are scored and 10 are unscored pretest questions. The outline does not say which ones are unscored, so treat every question as if it counts. You get 240 minutes to answer all of them, with two 10-minute breaks.
How much time do you get per PMP question?
You get 240 minutes for 180 questions, which is about 80 seconds per question on average. Case-study questions take longer to read, so you need to move faster on short single-answer questions. Timed full-length mock exams are the best way to build the right pace before exam day.
What type of questions are asked in the PMP exam?
Most questions are scenario-based and ask what a project manager should do first, next or best. The July 2026 outline lists single-response and multiple-response multiple choice, new case or scenario questions, new graphic-based questions, and, at test centres only, matching, enhanced matching, hotspot and pull-down list questions.
Are all PMP exam questions multiple choice?
No, not all of them. Most are multiple choice with one correct answer, but you will also see multiple-response questions where you pick two or more answers. Case and graphic-based questions appear in all modes. Matching, hotspot and pull-down formats appear only at test centres, according to PMI's July 2026 outline.
Which domain has the most PMP exam questions?
Process has the most questions at 41% of the exam. People is 33% and Business Environment is 26%, according to PMI's July 2026 exam content outline. Business Environment grew the most in this update, rising from 8%, so it deserves far more study time than it did in older preparation plans.
How many agile questions are on the PMP exam?
About 60% of the exam covers agile and hybrid approaches together, and about 40% covers predictive approaches, according to PMI's July 2026 outline. That means you need to be comfortable with sprints, backlogs, product owners and servant leadership, as well as baselines and change control in traditional projects.
Did the PMP exam questions change in 2026?
Yes. PMI updated the PMP exam in July 2026. The new outline adds AI, sustainability and stakeholder engagement in project-based scenarios, focuses more on outcomes and business value, and changes the domain weights. It also adds two new question types: case or scenario questions and graphic-based questions.
What are case study questions on the PMP exam?
Case study questions give you a longer project situation and then ask several questions based on it. They are new in the July 2026 outline. The first 10-minute break comes after the case-study section, and once you start that break, you cannot go back to the case-study questions.
What are graphic-based PMP questions?
Graphic-based questions ask you to read a visual, such as a burndown chart, a Kanban board, a schedule or a risk chart, and then choose the right answer or action. They are new in the July 2026 outline. Practise reading common project charts quickly so these questions do not slow you down.
Can I go back and review questions after a break?
No. According to PMI's July 2026 outline, once you start a break you cannot return to the section before it. So review any flagged questions in a section before you take the break. Plan your time so you have a few minutes for review at the end of each section.
Are PMP exam questions repeated from practice tests?
You should not expect to see your practice questions on the real exam. Practice questions from books, courses and websites are written to teach the same skills, but the real exam uses its own scenarios. Focus on learning the reasoning behind each answer rather than memorising specific questions or answer letters.
Should I use leaked PMP exam questions or dumps?
No. Lists that claim to be real or leaked PMP questions are not reliable, and memorising them does not build the judgement the exam tests. The exam is scenario-based, so you need to understand why an answer is best. Use original practice questions with explanations and the official exam content outline instead.
Is there a PMP exam questions and answers PDF?
You can save or print this page to use the 60 questions offline. Be careful with PDFs that claim to contain real exam questions, because they are often outdated or unreliable. Make sure any question bank you use matches PMI's July 2026 outline, with enough Business Environment, agile and hybrid questions.
Where can I find free PMP practice questions?
This article gives you 60 free, original practice questions with answers and explanations across all three domains. You can also build your own questions from the tasks in PMI's free July 2026 exam content outline. Whatever source you use, review every wrong answer and note why the correct option is better.
How many practice questions should I solve before the PMP exam?
There is no official number, but steady daily practice works best. Doing 20 to 30 questions a day with full review, followed by several full-length 180-question timed mocks, builds both judgement and stamina. Book your exam date only when your mock scores are steady across all three domains.
How do I answer PMP situational questions correctly?
Read the last line first to see whether it asks what to do first, next or best. Identify whether the setting is predictive, agile or hybrid. Remove options that escalate at once, ignore the problem or skip steps. Then pick the action a calm, proactive and collaborative project manager would take.
Are PMP exam questions hard?
Many candidates find them tricky because several options look reasonable. The questions test judgement in realistic situations, not simple recall of definitions. Long case studies and a 240-minute exam also test stamina. With regular practice, careful review of mistakes and timed mocks, most of the difficulty becomes manageable.
Does the PMP exam have math questions?
The exam focuses mainly on judgement, but you should still know basic calculations such as earned value. For example, cost performance index is earned value divided by actual cost, and schedule performance index is earned value divided by planned value. An index below 1 shows the project is over budget or behind schedule.
Are the 10 unscored PMP questions marked?
No. PMI's July 2026 outline says the exam has 170 scored questions and 10 unscored pretest questions, but it does not say which ones are unscored. Because you cannot identify them, treat every question as if it counts, give each one your full attention and do not skip any while you are in the exam.
Can I take the PMP exam online?
Yes. According to PMI's July 2026 outline, you can take the PMP exam in person at a Pearson VUE test centre or online with OnVue proctoring. The online exam includes single-response, multiple-response, case and graphic-based questions. Matching, hotspot and pull-down formats are only at test centres.
What happens if I fail the PMP exam?
You can take the exam up to three times within your one-year eligibility period. If you fail three times, you must wait one year from your last attempt before reapplying for PMP. Fees apply again for the second and third attempts, according to PMI's Certification Handbook revised in June 2026.
Can I reschedule my PMP exam if I am not ready?
Yes, but plan early. Rescheduling or cancelling within 30 days of your appointment costs US$70 plus taxes, about ₹6,633 as an approximate estimate. Within 48 hours of the exam, you lose all fees. That is why you should book only when your full-length mock scores are steady.
What should I study first for PMP exam questions?
Start with PMI's July 2026 exam content outline, which lists every task in the People, Process and Business Environment domains. Then study one domain at a time, spending the most time on Process at 41%. Practise questions after each topic so you apply what you learn straight away.
Does Brolly Academy provide PMP practice questions?
Brolly Academy's PMP course includes a dedicated PMP Exam Preparation module among its 13 modules, along with modules on hybrid project management, AI in project management and the business environment. The course runs as 35 contact hours of instructor-led training over 4 weeks, in classroom and online modes, with weekday and weekend batches.
Is Brolly Academy's PMP course in Hyderabad suitable for working professionals?
Yes. Brolly Academy offers weekday and weekend batches in both classroom and online modes, and online batches have flexible timings. The trainer, Mr. Raju, has more than 15 years of experience as a PMP trainer. Fees start from ₹10,999 for the Video Recording Plan, and EMI is available.
Learn with Brolly Academy
Review the syllabus, practical projects and batch timings, and book a free demo before you enrol.
Related Articles
Continue Your Learning
PMP Certification Course in Hyderabad
35 contact hours of instructor-led PMP exam preparation over 4 weeks: predictive, agile, hybrid, AI in project management and full exam practice.
View CourseScrum Master Training in Hyderabad
Scrum Guide 2020, Scrum events and artifacts, Jira, metrics, role plays and CSM, PSM I and SAFe exam preparation.
View CourseBusiness Analyst Course in Hyderabad
Requirements, BRD and user stories, UML, Agile, Jira, SQL, Excel and Power BI with capstone projects and placement support.
View Course